PROJECT WORKPLAN
LIFE DEMINE is divided in four different types of actions: preparatory actions (A), implementation actions (B), monitoring of the impact actions (C) dissemination actions (D), and an action for project management and monitoring (E). The project has started on July 2017 and is expected to be finished on June 2021. You can find more information on the development of these actions during the project at the Project Results section.
GRANTT CHART
Action | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | |||||||||||||||||||
Nº | Name of the action | I | II | III | IV | I | II | III | IV | I | II | III | IV | I | II | III | IV | I | II | III | IV | I | II | III | IV |
A. Preparatory actions | |||||||||||||||||||||||||
A.1 | Policy and legislation assessment | X | X | X | X | X | |||||||||||||||||||
A.2 | Assessment of the European mining sector. Characterisation of several mining effluents | X | X | ||||||||||||||||||||||
B. Implementation actions | |||||||||||||||||||||||||
B.1 | Process dessign, optimization and selection of the operationg parameters | X | X | X | X | ||||||||||||||||||||
B.2 | Design and construction of the innovative mining effluent treatment process | X | X | X | X | ||||||||||||||||||||
B.3 | Implementation and operation of the innovative mining effluent treatment process in Welsh abandoned mines | X | X | X | X | X | |||||||||||||||||||
B.4 | Implementation and operation of the innovative mining effluent treatment process in German mines | X | X | X | X | X | |||||||||||||||||||
B.5 | Replication and transderability od the obtained results | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X | ||||||||
C. Monitoring of the impact of the project actions | |||||||||||||||||||||||||
C.1 | Monitoring the project’s sustainability | X | X | X | X | X | X | X | X | X | |||||||||||||||
C.2 | Monitoring and measuring of the LIFE project performance indicators | X | X | X | X | X | X | X | X | ||||||||||||||||
D. Public awareness and dissemination of results | |||||||||||||||||||||||||
D.1 | Dissemination planning and development of the dissemination pack | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X | ||||||||
D.2 | Open days and networking | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X | ||||||||
E. Project management | |||||||||||||||||||||||||
E.1 | Project management and monitoring | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X |